After replacing a section of water main, what is the first procedure that must be carried out?

Prepare effectively for the Water License Class C Exam. Study with comprehensive quizzes and multiple-choice questions equipped with hints and explanations. Excel in your examination!

The first procedure that must be carried out after replacing a section of water main is pressure testing. This step is critical because it ensures that the newly installed section can withstand operational pressures without any leaks or failures. Pressure testing helps to confirm the integrity of the joints and the overall structural soundness of the water main.

By applying a specific amount of pressure, typically higher than normal operating conditions, operators can detect any weaknesses in the system. It is essential to accomplish this before disinfection, flushing, or taking water samples because any failure discovered during these subsequent steps could compromise the safety and functionality of the entire water distribution system. In addition, if the system does not pass the pressure test, it would require attention and possible repair before any further procedures could be safely conducted, ensuring that water quality standards are maintained throughout the process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy